PUBLIC
HEARING FOR SPECIAL ASSESSMENTS
MINUTES
Municipal
Complex - Assembly Room -
Town Chair
PRESENT:
Jerry Jurgensen, Supv. #3
Also Present: Randy Hager/Johnson Controls Bruce Sherman/Azco Inc. Matt Coenen/FVIC
Ken Coenen/FVIC Jack Wunderlich/Wunderlich-Hoffman
McMahon
Engineer
Randy
Hager/Johnson Cntrls. questioned the availability of travel on the roadway
during construction.
Bruce
Sherman/Azco Inc. questioned the portion charged to the businesses regarding
the recreation trail and stated the businesses would prefer keeping the land
rather than having the town construct a trail.
Engineer Sutter stated 20%
or $500,000 of the project is assessable to the businesses. He
will calculate the costs of the trail and get this information to him.
Dir. of Community Dev.
George Dearborn stated that approx. $939,000 will be received from the WI-DOT
as a grant for this project.
III. ADJOURNMENT
Respectfully
submitted,
Jeanne
Krueger, Certified Municipal Clerk