Pending Approval at the Reg.
Town Board
Meeting of June 25th, 2001
Meeting Of The
Building Committee
Municipal Complex - Assembly Room
Monday, June 11, 2001
4:30 p.m.
MINUTES
Present:
Town Chair, Arden Tews Supv. #1, Barbara Barczak Supv. #3, Jerry Jurgensen
Supv. #4, Russ Handevidt Town Clerk, Jeanne Krueger
Street Supt., Randy Gallow
Constr. Mgr., Mike Milbach
Project Supt., Les Much Citizen Member, Al Belmer
Town Admin., Patrick DeGrave Peter Mariahazy, Citizen Member
Excused: Supv. #2, Robert Sprague
Chairman Arden Tews
called the Building Committee meeting to order at 4:32 P.M.
Supt. Gallow,
Construction Manager Mike Milbach and Project Superintendent Les Much conducted
a walk-thru for the Building Committee.
They explained and updated the project including the status of lights,
doors, electric, beams, heat, ventilation, concrete, roof panels, fans, exhaust
system and site work. They also gave an
updated time-line stating the project was on time and on budget. Their expectations are to have the building
itself complete by August 1st.
MOTION Supv. Barczak,
second Supv. Jurgensen to adjourn the Building Committee at 5:05 P.M. Motion carried unanimously.
Respectfully
Submitted,
Jeanne A. Krueger,
CMC